The installation and operation of the pulverizer equipment has been introduced in the previous article. However, the content of these knowledge is not enough. We also need to know more, so we can continue to deeply and extensive, so that you can fully understand the crusher equipment soon, let yourself be more professional in this area. The following content will be mainly concentrated in its general provisions and the two aspects of the test, as follows.
1. General provisions
(1) Crusher equipment drivers should be trained and assessment, knowing and familiar with "three understandings" and "four sessions", but also to hold the certificate.
(2) It is necessary to cooperate with the conveyor driver, unified signal connection, and stop according to the order.
(3) When the pulverizer is added, there should be a large block of material to avoid clogging or damage the equipment.
2. Before the test
(1) equipment should be installed on the basis of horizontal concrete and securely secured.
(2) Before installing the crusher equipment, pay attention to the body and the level should be vertical.
(3) After the mounting of the pulverizer equipment is completed, it will be able to test everything after all problems.
3. Try
(1) After verifying everything, it is possible to issue a boot signal.
(2) Crusher equipment In the test process, pay attention to whether the equipment is operating normally, whether the bearing temperature exceeds the specified temperature, and whether the temperature of the motor is normal.
(3) Safety devices such as the protection net of the pulverizer equipment should be kept intact. And often check frequently during the work, if it is damaged, it should be replaced immediately.